It's now mid-July, and I suspect that the OpenACS4 Schedule at https://openacs.org/4/schedule could usefully be updated to reflect current reality of the porting process.

As far as I can tell, we didn't release the OpenACS4 core in alpha on 01 June, nor in beta on 30 June, making the listed 31 July date for a final release' of the core look decidedly unlikely.

I'm actually impressed at how much progress has been made with the port -- well done to all who have worked on it! But for outsiders looking in, it would probably help the 'image' of OpenACS as a whole if the schedule was kept a bit more up to date.

On a related note, in the same text box on the https://openacs.org/ page which links to the schedule, there is a title of "User Guide (June 2001)" which should probably be updated to August 2001?