Don is going to be away next week on a hawk-banding expedition, so he
won't be around to "bless" the code and declare it ready for testing.
We figured that we might as well give everyone the week to finish up
their work, especially since it looks like we've got a lot of coding
being frantically finished up this weekend. :)
The new freeze date is a week from *Monday*, not Sunday, which makes
it 9/23. The rest of the dates will slide accordingly; beta will be
on 10/7 and the release on 10/21, all Mondays.
I will attempt to update the status page
(http://dev.openacs.org/projects/openacs/4.6/project-status) at least
once a day, when there are updates to be made, so folks can see how we
are progressing.