A couple of things:

1) Unless anyone protests loudly, Nick and I are going to require Postgres 7.3.x for project-manager. It just makes life easier. You will be able to use 7.2.x if you recompile it to support more than 16 arguments.

2) Nick is working on adding back in the edit project functionality, with the content repository.

3) I've started writing up a content repository document: http://rubick.com:8002/openacs/content_repository  I needed to write it in order to figure out how the CR works.

4) I'm starting work on the Tasks. It will use the content repository.

5) I'd love to know how to use acs-events or the calendar package to store dates. I haven't had the time to look into it yet. Does anybody have any documentation on this? Or a good example to refer to? Anybody have any time to look into this?

6) Constraints does seem like better terminology than dependencies. Any objections?

7) I haven't done much thinking about resources yet.

8) More developers are very welcome to work on this. Or if you have feature requests, feel free to file them in the bug-tracker.